Which of the following is true of the schedule performance index (SPI)?

A.It means that a project is behind

schedule if an SPI is greater than one.

B.It can be used to estimate the projected time to complete the project.

C. It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.

D. It is the ratio of planned value to actual costs.